Fire-Rated Casework It attaches to the assembly, not the drawing.

A fire rating does not attach to a drawing. It attaches to a tested assembly, and it belongs to whoever holds the test evidence for it. Understanding that distinction is the difference between documenting a rated item correctly and creating a problem nobody notices until inspection.

What a rating actually attaches to

A tested assembly.
A rating is achieved by a specific construction, in a specific configuration, tested under a defined method. Change the construction and the evidence no longer applies to it.
A product and its manufacturer.
Rated doors, panels and assemblies are supplied by manufacturers who hold the test evidence for what they produce.
Not a drawing, and not a detailer.
A drawing can specify and locate a rated assembly. It cannot confer the rating, and no amount of detailing makes an untested construction rated.
Casework section where a rated assembly meets a wall, showing the junction detail and the specification reference
Rated conditions drawn as junctions and references rather than as a claim.

What the specification obliges

Which items require a rating, and what rating.
Named in the specification, and frequently varying between locations in the same building.
How the rated item meets what surrounds it.
The junction between a rated assembly and the construction around it is usually where the requirement is either satisfied or lost.
Which components may be substituted, and which may not.
Substitution on a rated assembly is a different question from substitution elsewhere, because the evidence attaches to the tested configuration.
What evidence the project requires and when.
Certificates, test references and product data, with lead time that belongs in the programme.

Who holds the credential

The testing authority conducts the test
and issues the evidence.
The manufacturer holds the certification
for the assembly it produces, and supplies it as part of the product.
The fabricator carries the obligation
to build what the specification requires and to install it so the rating is not compromised.
BluEnt detailing does none of these.
We detail to what the specification imposes and report what it requires. We do not test, rate, certify or approve any assembly, we do not issue compliance certification, and we are not a certifying authority.

What detailing can do is make sure the rated item is identified, located, dimensioned and detailed at its junctions so the requirement is visible rather than assumed.

What a drawing can and cannot carry

The drawing can
The drawing cannot
Identify which items the specification requires to be rated
Confer a rating on any assembly
Reference the specified product and its rating
Substitute for the manufacturer's test evidence
Detail the junction where a rated item meets adjacent construction
Guarantee the installed condition performs
Show fixing and clearance so the installed condition matches what was specified
Approve a substitution on a rated assembly
Flag where the drawn condition may compromise the requirement
Certify compliance to any authority
Identify evidence and lead-time obligations for the programme
Issue or hold certification

Where packages fail against it

A rating priced as standard casework.
The requirement is in the specification, reads as a note, and the product cost and lead time are not in the number.
A substitution made on a rated item.
Legitimate elsewhere, and on a rated assembly it invalidates the evidence unless the alternative carries its own.
The junction ignored.
The item is correct and the condition around it is not, which is where the requirement is most often lost.
Evidence assumed to arrive with the drawing.
It arrives with the product, from the manufacturer, and it has to be requested.

Services and sectors that apply

Answers

Common questions

Can you produce fire-rated casework drawings?
We produce documentation for casework the specification requires to be rated. The rating itself attaches to a tested assembly and the manufacturer who holds the evidence for it. A drawing identifies, locates and details the item; it does not confer the rating.
Do you certify that the assembly complies?
No. We do not test, rate, certify or approve assemblies, and we are not a certifying authority. Findings and requirements are reported.
Can a rated item be substituted?
That is a question for the specification and the design team, not for the drawing. Test evidence attaches to a tested configuration, so an alternative needs evidence of its own. Where a substitution is proposed, it is raised as a request rather than drawn.
Who supplies the certification?
The manufacturer of the rated assembly, as part of the product. It is requested, and its lead time belongs in the programme.

Rating requirements are cheap to find in a specification

And expensive to find at inspection.

  • Rated items identified, located and detailed at their junctions
  • No testing, rating, certification or approval capability claimed
  • Evidence and lead-time obligations identified for the programme
  • One named contact, not a general queue

Get a Free Drawing Review

See a sample set drawn to this standard

Scope and questions come back, not a template.

  • This field is for validation purposes and should be left unchanged.
  • Accepted file types: pdf, dwg, Max. file size: 100 MB.

Reserve Your
Meeting Slot Today!

Contact Now

Connect with us!

Let's Talk Fixed form

Let's Talk

"*" indicates required fields

This field is for validation purposes and should be left unchanged.
Services We Offer*
Subscribe to Newsletter
Go up